Illinois 157 And East Leg Of Illinois 162 Anticipated To Reopen In Madison County

Northbound and southbound Illinois 157 and the east leg of Illinois 162 in Glen Carbon are scheduled to reopen Oct. 26, 2026, while the west leg remains closed for construction.

Dawn Johnson - Illinois Department of Transportation
Save Share
Listen to the story

Illinois 157 in Madison CountyGLEN CARBON – The Illinois Department of Transportation announced today that northbound and southbound Illinois 157 and the east leg of Illinois 162 in Glen Carbon are scheduled to reopen to traffic, weather permitting, Monday, Oct. 26, 2026.

The west leg of Illinois 162 will remain closed as construction continues on the new road and bridge.

Get The Latest News!

Don't miss our top stories and need-to-know news everyday in your inbox.

Sign in to hide this notification.

Article continues after sponsor message

The $17.6 million project includes realigning Illinois 162 to create a signalized four-way intersection, bridge construction and bicycle and pedestrian accommodations. Completion of the overall project is expected by July 31, 2027.

During the continued closure, marked detours will be in place for Illinois 162 traffic:

  • Westbound Illinois 162: Take Illinois 157 northbound to Interstate 270 westbound, then Interstate 255 southbound to Illinois 162.
  • Eastbound Illinois 162: Take Interstate 255 northbound to Interstate 270 eastbound, then Illinois 157 southbound to Illinois 162.

Motorists are encouraged to avoid the area and plan alternate routes ahead of time. Drivers should expect delays on the alternate routes and be prepared to adjust their route as needed. Please reduce speed, be alert for changing conditions, obey all construction signage, and refrain from using mobile devices while approaching and traveling through the work zone.

Over the next six years, IDOT is planning to improve 7,107 lane miles of highway and 8.4 million square feet of bridge deck as part of Rebuild Illinois, which is investing $33.2 billion into all modes of transportation. Accomplishments through Year Seven of Rebuild Illinois include $25.6 billion of improvements statewide to 24,498 lane miles of highway, 959 bridges and 1,475 additional safety improvements.

Article continues after sponsor message

For IDOT District 8 updates, follow us on the social media platform X at @IDOTDistrict8 or view area construction details on IDOT’s traveler information map on GettingAroundIllinois.com.

Prefer RiverBender on Google
Copyright 2026 Riverbender.com. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.

 

More like this:

Lane And Ramp Closures On I-55/70 In Madison County Begin Oct. 19
4 days ago
I-55 Lane Closures At Illinois 140 Bridge In Madison County Start Aug. 17, 2026
Aug 12, 2026
Early Monday Morning, Sept. 21, 2026, I-270 Crash Leaves Dupo Woman Dead
Sep 21, 2026
Lanes Reopening For Labor Day Holiday Travel
Sep 3, 2026
Pierce Lane, West Delmar Closures in Madison County Begin Aug. 17, 2026
Aug 12, 2026