Edwardsville Accepts $21M Grant For Goshen Road/Lincoln Trail Project

Major roadway reconstruction project will bring three roundabouts, new shared use path, updated bus stop, additional bicycle parking and more using federal funds.

Save Share
Listen to the story

Plummer Family Park in Edwardsville.EDWARDSVILLE – The largest grant ever received in Edwardsville history will go towards a major reconstruction project to bring multimodal transportation upgrades near Plummer Family Park.

Aldermen approved three related agreements at their Oct. 20, 2026 City Council meeting, including one with the U.S. Department of Transportation regarding a grant of over $21 million for the Goshen Road and Lincoln Trail Project.

Get The Latest News!

Don't miss our top stories and need-to-know news everyday in your inbox.

Sign in to hide this notification.

Public Works Director Ryan Zwijack said the city received a $21,241,730 grant under the DOT’s RAISE program in 2024, adding: “We’re ready to kick-start and get this going.”

Article continues after sponsor message

Mayor Art Risavy thanked Zwijack and his staff for their work on the project, which Zwijack said has been five years in the making.

“This the biggest grant, by far, that we’ve ever received,” Risavy said. “Talk about a game changer for that end of town, and not really just for that end of town because of how many people go out to Plummer Family Park. Now you can ride your bike there and be safe on the streets.”

The project will bring about 1.75 miles of roadway reconstruction along Goshen Road and Old Troy Road. It will also add three roundabouts at the intersections of Goshen Road with Gerber Road, District Drive and Ridgeview Road.

A new Liberty Trail shared-use path measuring approximately 2.9 miles will be built along Old Troy Road and Goshen Road as part of the project, which also includes plans for an updated bus stop at Friar Tucks on Target Drive and three bicycle parking facilities.

A related agreement agreement with Oates Associates to perform preliminary engineering and design work on the same project was also approved for a total of $3,076,366. Since $2,583,000 of this amount will be covered by the federal grant funds, Zwijack said the city’s share of engineering costs is just under $500,000.

Article continues after sponsor message

The third agreement, a joint funding agreement with the Illinois Department of Transportation (IDOT), allows the state agency to handle the federal funds for the large-scale construction project, while the city facilitates the work on the project itself. Zwijack said this is the most efficient way of handling projects of this size.

Zwijack said he hopes to have the project out for bid in 2029, with construction expected to begin in 2030. Once construction begins, Zwijack estimated a completion timeline of two years.

Prefer RiverBender on Google
Be part of the next local story. Behind every headline is the work of covering our community. Support RiverBender with a subscription and help make that work possible.
Support Local Journalism
Copyright 2026 Riverbender.com. All rights reserved. This material may not be published, broadcast, rewritten, or redistributed.

 

More like this:

Glen Carbon Buys Electric Vehicle Charging Station For Schon Park
Sep 22, 2026
Village of Glen Carbon Awarded Nearly $300,000 Grant For Illinois-157 Shared-Use Path
Aug 18, 2026
Alton Advances Grant Application For East Broadway Crosswalk Upgrades
Sep 21, 2026
Madison County Board Approves Full Agenda, Including Road Projects and County Purchases
5 days ago
MCT Opens 1.5-Mile Ridge Prairie Trail in Collinsville
Sep 24, 2026