While water and sewer improvements in Sister Bay are on track to start next month and finish before summer, a road construction project for Highway 42 has been pushed back a year. Jeremy Ashauer of the Department of Transportation says documents concerning public right-of-way for highway 42 in Sister Bay were uncovered after much of the project planning was done.
This means some land that was thought to be in the right-of-way will need to be acquired, and that process is expected to take up to a year. Instead of the construction starting next summer it will start in 2015.